Facility/NSW/Prepare EIS
23–25 Waterloo Road Data Centre
Facility in Macquarie Park, NSW · Project proponent
The record
- Status
- Proposed
announced or lodged for approval - Capacity as stated
- 70 MW70 MW total power consumption
- Operator
- Project proponent
- Record type
- Facility
one building or site - Location
- Macquarie Park, New South Wales
Show on the map (approximate) - Evidence grade
- REPORTED
it rests on a credible secondary source or the applicant's own description - Last checked
- 8 Oct 2026
- NSW application
- SSD-91297457
- Source
- NSW Planning Portal
On the NSW planning register
State significant development
- Application
- SSD-91297457
- Current stage
- Prepare EIS (register checked 2 Nov 2026)
- Decision
- Not yet decided
- Determination date
- —
- Council
- City of Ryde
- Register page
- 23-25 Waterloo Road Data Centre
- 29 daysRequest for SEARs to SEARs issued
- 440 days (14.5 months)Still open: SEARs requested to today
Dated milestones
- 18 Aug 2025SEARs requested (first document uploaded)Dated by document upload time
- 16 Sep 2025SEARs issued (first document uploaded)Dated by document upload time
Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.
Stage changes we've recorded
No stage change since our captures began on 8 October 2026.
NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.
More