RegularsAIData centre tracker

NSW State significant register/data centres

How long NSW data centre approvals take

378days

From the EIS exhibition opening to the decision, NSW data centre approvals took a median of 378 days (19 decided projects; shortest 158, longest 1,022).

Data as at 1 November 2026. Dates come from the project pages, the upload times the portal stamps on documents, the department's own assessment reports and our captures.

Exhibition to decision · one line per application

How long each approval took

How long each NSW data centre approval took22 State significant data centre applications, each drawn from the day its EIS went on exhibition to the day it was decided, grouped by the year of the decision, or to today if it is still waiting. Median 378 days.06 mo1 yr18 mo2 yr30 mo3 yr2022Station Road Data Centre Expansion: 158 days, exhibition 11 July 2022 to decision 16 December 2022Station Road202351 Huntingwood Drive Data Centre: 238 days, exhibition 20 January 2023 to decision 15 September 202351 Huntingwood Drive2024Talavera Road Data Centre Campus Expansion: 792 days, exhibition 18 November 2021 to decision 19 January 2024Talavera RoadProject Echidna Data Centre Eastern Creek: 302 days, exhibition 8 June 2023 to decision 5 April 2024Project EchidnaGrand Avenue Data Centre Expansion, Rosehill: 416 days, exhibition 27 October 2023 to decision 16 December 2024Grand AvenueDavis Road Data Centre (Cundall): 276 days, exhibition 19 March 2024 to decision 20 December 2024Davis Road2025Lanceley Place Data Centre, Artarmon: 282 days, exhibition 3 July 2024 to decision 11 April 2025Lanceley PlaceApollo Place Data Centre: 357 days, exhibition 17 October 2024 to decision 9 October 2025Apollo Place43-61 Turner Road Data Centre: 261 days, exhibition 5 March 2025 to decision 21 November 202543-61 Turner RoadMarsden Park Data Centre: 378 days, exhibition 14 November 2024 to decision 27 November 2025Marsden ParkProject Duke Data Centre: 402 days, exhibition 15 November 2024 to decision 22 December 2025Project DukeDigiCo SYD1 Data Centre Expansion: 235 days, exhibition 2 May 2025 to decision 23 December 2025DigiCo SYD1NEXTDC S4 Data Centre Horsley Park: 516 days, exhibition 26 July 2024 to decision 24 December 2025NEXTDC S420261-5 Khartoum Road Data Centre: 370 days, exhibition 6 March 2025 to decision 11 March 20261-5 Khartoum RoadProject Pluto Data Centre: 440 days, exhibition 9 May 2025 to decision 23 July 2026Project PlutoProject Apollo Data Centre Macquarie Park: 530 days, exhibition 21 March 2025 to decision 2 September 2026Project ApolloGlendenning Road Data Centre: 486 days, exhibition 16 May 2025 to decision 14 September 2026Glendenning RoadHoneman Close Data Centre: 1022 days, exhibition 14 December 2023 to decision 1 October 2026Honeman CloseRoad 1 Data Centre: 385 days, exhibition 11 September 2025 to decision 1 October 2026Road 1waitingJulius Avenue Data Centre: still waiting, 458 days since the EIS exhibition opened on 31 July 2025Julius Avenue458 days and countingKurri Kurri Data Centre: still waiting, 18 days since the EIS exhibition opened on 14 October 2026Kurri Kurri18 days and countingNEXTDC S4 Data Centre Phase 2, Horsley Park: still waiting, 19 days since the EIS exhibition opened on 13 October 2026NEXTDC S419 days and countingmedian 378 daysHow long each NSW data centre approval took22 State significant data centre applications, each drawn from the day its EIS went on exhibition to the day it was decided, grouped by the year of the decision, or to today if it is still waiting. Median 378 days.01 yr2 yr3 yr2022Station Road Data Centre Expansion: 158 days, exhibition 11 July 2022 to decision 16 December 2022202351 Huntingwood Drive Data Centre: 238 days, exhibition 20 January 2023 to decision 15 September 20232024Talavera Road Data Centre Campus Expansion: 792 days, exhibition 18 November 2021 to decision 19 January 2024Project Echidna Data Centre Eastern Creek: 302 days, exhibition 8 June 2023 to decision 5 April 2024Grand Avenue Data Centre Expansion, Rosehill: 416 days, exhibition 27 October 2023 to decision 16 December 2024Davis Road Data Centre (Cundall): 276 days, exhibition 19 March 2024 to decision 20 December 20242025Lanceley Place Data Centre, Artarmon: 282 days, exhibition 3 July 2024 to decision 11 April 2025Apollo Place Data Centre: 357 days, exhibition 17 October 2024 to decision 9 October 202543-61 Turner Road Data Centre: 261 days, exhibition 5 March 2025 to decision 21 November 2025Marsden Park Data Centre: 378 days, exhibition 14 November 2024 to decision 27 November 2025Project Duke Data Centre: 402 days, exhibition 15 November 2024 to decision 22 December 2025DigiCo SYD1 Data Centre Expansion: 235 days, exhibition 2 May 2025 to decision 23 December 2025NEXTDC S4 Data Centre Horsley Park: 516 days, exhibition 26 July 2024 to decision 24 December 202520261-5 Khartoum Road Data Centre: 370 days, exhibition 6 March 2025 to decision 11 March 2026Project Pluto Data Centre: 440 days, exhibition 9 May 2025 to decision 23 July 2026Project Apollo Data Centre Macquarie Park: 530 days, exhibition 21 March 2025 to decision 2 September 2026Glendenning Road Data Centre: 486 days, exhibition 16 May 2025 to decision 14 September 2026Honeman Close Data Centre: 1022 days, exhibition 14 December 2023 to decision 1 October 2026Road 1 Data Centre: 385 days, exhibition 11 September 2025 to decision 1 October 2026waitJulius Avenue Data Centre: still waiting, 458 days since the EIS exhibition opened on 31 July 2025Julius Avenue, 458 days and countingKurri Kurri Data Centre: still waiting, 18 days since the EIS exhibition opened on 14 October 2026Kurri Kurri, 18 days and countingNEXTDC S4 Data Centre Phase 2, Horsley Park: still waiting, 19 days since the EIS exhibition opened on 13 October 2026NEXTDC S4, 19 days and countingmedian 378 daysLongest: Honeman Close, 1,022 d · shortest: Station Road, 158 d
Grouped by the year of the decision. Dashed: still waiting.

Where the time goes

In the pipeline report

The wait above runs from exhibition to decision. The pipeline report breaks it down stage by stage, from the request for SEARs to the decision (14 measured steps): the median, middle half and range for each step, so you can see where approvals stall. It also lists the 18 NSW applications not yet decided, nearest a decision first, with the power each one states.

Get the free sample What's in the report

Approvals per year

By decision date

NSW data centre approvals per year
YearNewModsMedian days
202210158 (1)
202310238 (1)
202441359 (4)
202572357 (7)
2026 (to 1 Nov 2026)66463 (6)

The current year is the year to date. Megawatts approved each year are in the pipeline report.

NSW data centre approvals per year, and the median wait2022: 1 new projects, 0 modifications, median wait 158 days; 2023: 1 new projects, 0 modifications, median wait 238 days; 2024: 4 new projects, 1 modifications, median wait 359 days; 2025: 7 new projects, 2 modifications, median wait 357 days; 2026: 6 new projects, 6 modifications, median wait 463 days12022158 d12023238 d412024359 d722025357 d662026*463 dNSW data centre approvals per year, and the median wait2022: 1 new projects, 0 modifications, median wait 158 days; 2023: 1 new projects, 0 modifications, median wait 238 days; 2024: 4 new projects, 1 modifications, median wait 359 days; 2025: 7 new projects, 2 modifications, median wait 357 days; 2026: 6 new projects, 6 modifications, median wait 463 days12022158 d12023238 d412024359 d722025357 d662026*463 d
New data centre projects and modifications approved each year on the NSW State significant register, by decision date, with each year's median wait. Council approvals aren't included.

What this doesn't cover

  • Council approvals. Smaller data centres approved by councils aren't on the State significant register, so these counts are a floor.
  • Stage history before our captures. We began capturing the register on 8 October 2026; earlier stage changes are dated only where a document or report dates them.
  • Dates as stated. Dates from assessment reports are as the department states them; an upload time marks when a document went up, which can be after the event.

NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.