Campus/VIC
Vantage MEL1
Campus in Tullamarine, VIC · Vantage Data Centers
The record
- Status
- Operational
operating today, according to the operator or a primary source - Capacity as stated
- 64 MW64 MW IT at full build
- Operator
- Vantage Data Centers
- Record type
- Campus
several buildings on one site - Location
- Tullamarine, Victoria
Show on the map (approximate) - Evidence grade
- SOLID
a primary document or direct operator disclosure confirms it - Last checked
- 21 Oct 2026
- NSW application
- Not on the NSW register
- Source
- Vantage Data Centers
More
Track the whole pipeline. The quarterly pipeline report covers every sourced project, the decisions to watch and a spreadsheet.
Spotted something wrong or out of date? Tell us, with a source if you can. Material changes are dated in the corrections log.