Facility/NSW/Withdrawn

52 Turner Road Data Centre

Facility in Gregory Hills, NSW · Project proponent

The record

Status
Withdrawn
withdrawn by the applicant, kept for the record
Capacity as stated
40 MW40 MW capacity (withdrawn proposal)
Operator
Project proponent
Record type
Facility
one building or site
Location
Gregory Hills, New South Wales
Show on the map (approximate)
Evidence grade
SOLID
a primary document or direct operator disclosure confirms it
Last checked
8 Oct 2026
NSW application
SSD-60185233

On the NSW planning register

State significant development

Application
SSD-60185233
Current stage
Withdrawn (register checked 2 Nov 2026)
Decision
Not yet decided
Determination date
—
Council
Camden
Register page
52 Turner Road Data Centre

Dated milestones

  1. 20 Jul 2023SEARs issued (first document uploaded)Dated by document upload time

Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.

Stage changes we've recorded

No stage change since our captures began on 8 October 2026.

NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.

More

Track the whole pipeline. The quarterly pipeline report covers every sourced project, the decisions to watch and a spreadsheet.

Spotted something wrong or out of date? Tell us, with a source if you can. Material changes are dated in the corrections log.