Facility/NSW/Withdrawn
52 Turner Road Data Centre
Facility in Gregory Hills, NSW · Project proponent
The record
- Status
- Withdrawn
withdrawn by the applicant, kept for the record - Capacity as stated
- 40 MW40 MW capacity (withdrawn proposal)
- Operator
- Project proponent
- Record type
- Facility
one building or site - Location
- Gregory Hills, New South Wales
Show on the map (approximate) - Evidence grade
- SOLID
a primary document or direct operator disclosure confirms it - Last checked
- 8 Oct 2026
- NSW application
- SSD-60185233
- Source
- NSW Planning Portal
On the NSW planning register
State significant development
- Application
- SSD-60185233
- Current stage
- Withdrawn (register checked 2 Nov 2026)
- Decision
- Not yet decided
- Determination date
- —
- Council
- Camden
- Register page
- 52 Turner Road Data Centre
Dated milestones
- 20 Jul 2023SEARs issued (first document uploaded)Dated by document upload time
Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.
Stage changes we've recorded
No stage change since our captures began on 8 October 2026.
NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.