RegularsAIData centre tracker

Facility/NSW/Determination

Station Road Data Centre Expansion

Facility in Seven Hills, NSW · Microsoft

The record

Status
Committed
approved or otherwise committed, but construction isn't confirmed
Capacity as stated
Capacity not stated on portal
Operator
Microsoft
Record type
Facility
one building or site
Location
Seven Hills, New South Wales
Show on the map (approximate)
Evidence grade
SOLID
a primary document or direct operator disclosure confirms it
Last checked
8 Oct 2026
NSW application
SSD-33781208

On the NSW planning register

State significant development

Application
SSD-33781208
Current stage
Determination (register checked 2 Nov 2026)
Decision
Approved
Determination date
16/12/2022
Council
Blacktown
Register page
Station Road Data Centre Expansion

158 days from exhibition to decision: quicker than 19 of the 19 decided NSW data centre approvals.

decidedmedian 37801 yr2 yr3 yr
Each tick in the top row is one decided application; the line below is this one. Every approval, timed.

Dated milestones

  1. 16 Dec 2021SEARs requested (first document uploaded)Dated by document upload time
  2. 24 Dec 2021SEARs issued (first document uploaded)Dated by document upload time
  3. 14 Apr 2022EIS lodged (first document uploaded)Dated by document upload time
  4. 11 Jul 2022EIS exhibition startsDated by assessment report
  5. 11 Jul 2022Notice of exhibition publishedDated by document upload time
  6. 8 Aug 2022EIS exhibition closesDated by assessment report
  7. 30 Aug 2022Response to submissions lodged (first document uploaded)Dated by document upload time
  8. 19 Sep 2022Applicant's submissions report receivedDated by assessment report
  9. 16 Dec 2022Determined: ApprovedDated by page field
  10. 16 Dec 2022Determination documents first publishedDated by document upload time

Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.

Stage changes we've recorded

No stage change since our captures began on 8 October 2026.

NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.

More

Track the whole pipeline. The quarterly pipeline report covers every sourced project, the decisions to watch and a spreadsheet.

Spotted something wrong or out of date? Tell us, with a source if you can. Material changes are dated in the corrections log.