Facility/NSW/Determination
Station Road Data Centre Expansion
Facility in Seven Hills, NSW · Microsoft
The record
- Status
- Committed
approved or otherwise committed, but construction isn't confirmed - Capacity as stated
- Capacity not stated on portal
- Operator
- Microsoft
- Record type
- Facility
one building or site - Location
- Seven Hills, New South Wales
Show on the map (approximate) - Evidence grade
- SOLID
a primary document or direct operator disclosure confirms it - Last checked
- 8 Oct 2026
- NSW application
- SSD-33781208
- Source
- NSW Planning Portal
On the NSW planning register
State significant development
- Application
- SSD-33781208
- Current stage
- Determination (register checked 2 Nov 2026)
- Decision
- Approved
- Determination date
- 16/12/2022
- Council
- Blacktown
- Register page
- Station Road Data Centre Expansion
158 days from exhibition to decision: quicker than 19 of the 19 decided NSW data centre approvals.
Dated milestones
- 16 Dec 2021SEARs requested (first document uploaded)Dated by document upload time
- 24 Dec 2021SEARs issued (first document uploaded)Dated by document upload time
- 14 Apr 2022EIS lodged (first document uploaded)Dated by document upload time
- 11 Jul 2022EIS exhibition startsDated by assessment report
- 11 Jul 2022Notice of exhibition publishedDated by document upload time
- 8 Aug 2022EIS exhibition closesDated by assessment report
- 30 Aug 2022Response to submissions lodged (first document uploaded)Dated by document upload time
- 19 Sep 2022Applicant's submissions report receivedDated by assessment report
- 16 Dec 2022Determined: ApprovedDated by page field
- 16 Dec 2022Determination documents first publishedDated by document upload time
Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.
Stage changes we've recorded
No stage change since our captures began on 8 October 2026.
NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.
More
Track the whole pipeline. The quarterly pipeline report covers every sourced project, the decisions to watch and a spreadsheet.
Spotted something wrong or out of date? Tell us, with a source if you can. Material changes are dated in the corrections log.