STACK SYD01
Campus in Western Sydney, NSW · STACK Infrastructure
The record
- Status
- Proposed
announced or lodged for approval - Capacity as stated
- 450 MW450 MW (application)
- Operator
- STACK Infrastructure
- Record type
- Campus
several buildings on one site - Location
- Western Sydney, New South Wales
Show on the map (approximate) - Evidence grade
- SOLID
a primary document or direct operator disclosure confirms it - Last checked
- 21 Oct 2026
- NSW application
- SSD-82211208
- Source
- NSW Planning Portal
On the NSW planning register
State significant development
- Application
- SSD-82211208
- Current stage
- More Information Required (register checked 2 Nov 2026)
- Decision
- Not yet decided
- Determination date
- —
- Council
- Penrith
- Register page
- STACK SYD01 Data Centre, Erskine Park
- 25 daysRequest for SEARs to SEARs issued
- 214 days (7.0 months)SEARs issued to EIS lodged
- 594 days (19.5 months)Still open: SEARs requested to today
Dated milestones
- 17 Mar 2025SEARs requested (first document uploaded)Dated by document upload time
- 11 Apr 2025SEARs issued (first document uploaded)Dated by document upload time
- 11 Nov 2025EIS lodged (first document uploaded)Dated by document upload time
- 5 Dec 2025Notice of exhibition publishedDated by document upload time
- 4 Feb 2026Response to submissions lodged (first document uploaded)Dated by document upload time
Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.
Stage changes we've recorded
No stage change since our captures began on 8 October 2026.
NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.