STACK SYD01

Campus in Western Sydney, NSW · STACK Infrastructure

The record

Status
Proposed
announced or lodged for approval
Capacity as stated
450 MW450 MW (application)
Operator
STACK Infrastructure
Record type
Campus
several buildings on one site
Location
Western Sydney, New South Wales
Show on the map (approximate)
Evidence grade
SOLID
a primary document or direct operator disclosure confirms it
Last checked
21 Oct 2026
NSW application
SSD-82211208

On the NSW planning register

State significant development

Application
SSD-82211208
Current stage
More Information Required (register checked 2 Nov 2026)
Decision
Not yet decided
Determination date
—
Council
Penrith
Register page
STACK SYD01 Data Centre, Erskine Park
  • 25 daysRequest for SEARs to SEARs issued
  • 214 days (7.0 months)SEARs issued to EIS lodged
  • 594 days (19.5 months)Still open: SEARs requested to today

Dated milestones

  1. 17 Mar 2025SEARs requested (first document uploaded)Dated by document upload time
  2. 11 Apr 2025SEARs issued (first document uploaded)Dated by document upload time
  3. 11 Nov 2025EIS lodged (first document uploaded)Dated by document upload time
  4. 5 Dec 2025Notice of exhibition publishedDated by document upload time
  5. 4 Feb 2026Response to submissions lodged (first document uploaded)Dated by document upload time

Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.

Stage changes we've recorded

No stage change since our captures began on 8 October 2026.

NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.

More

Track the whole pipeline. The quarterly pipeline report covers every sourced project, the decisions to watch and a spreadsheet.

Spotted something wrong or out of date? Tell us, with a source if you can. Material changes are dated in the corrections log.