Facility/NSW/Determination
Project Echidna Data Centre Eastern Creek
Facility in Eastern Creek, NSW · Project proponent
The record
- Status
- Under construction
construction has started - Capacity as stated
- 35 MW35 MW operational capacity (design description)
- Operator
- Project proponent
- Record type
- Facility
one building or site - Location
- Eastern Creek, New South Wales
Show on the map (approximate) - Evidence grade
- SOLID
a primary document or direct operator disclosure confirms it - Last checked
- 8 Oct 2026
- NSW application
- SSD-47320208
- Source
- NSW Planning Portal
On the NSW planning register
State significant development
- Application
- SSD-47320208
- Current stage
- Determination (register checked 2 Nov 2026)
- Decision
- Approved
- Determination date
- 05/04/2024
- Council
- Blacktown
- Register page
- Project Echidna Data Centre Eastern Creek
302 days from exhibition to decision: quicker than 13 of the 19 decided NSW data centre approvals.
Dated milestones
- 15 Aug 2022SEARs requested (first document uploaded)Dated by document upload time
- 17 Aug 2022SEARs issued (first document uploaded)Dated by document upload time
- 7 Oct 2022EIS lodged (first document uploaded)Dated by document upload time
- 8 Jun 2023EIS exhibition startsDated by assessment report
- 8 Jun 2023Notice of exhibition publishedDated by document upload time
- 5 Jul 2023EIS exhibition closesDated by assessment report
- 19 Sep 2023Applicant's submissions report receivedDated by assessment report
- 19 Sep 2023Response to submissions lodged (first document uploaded)Dated by document upload time
- 5 Apr 2024Determined: ApprovedDated by page field
- 5 Apr 2024Determination documents first publishedDated by document upload time
Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.
Stage changes we've recorded
No stage change since our captures began on 8 October 2026.
NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.
More
Track the whole pipeline. The quarterly pipeline report covers every sourced project, the decisions to watch and a spreadsheet.
Spotted something wrong or out of date? Tell us, with a source if you can. Material changes are dated in the corrections log.