Facility/NSW/Determination
Project Duke Data Centre
Facility in Mascot, NSW · Project proponent
The record
- Status
- Committed
approved or otherwise committed, but construction isn't confirmed - Capacity as stated
- 90 MVA (register description)
- Operator
- Project proponent
- Record type
- Facility
one building or site - Location
- Mascot, New South Wales
Show on the map (approximate) - Evidence grade
- SOLID
a primary document or direct operator disclosure confirms it - Last checked
- 8 Oct 2026
- NSW application
- SSD-71368959
- Source
- NSW Planning Portal
On the NSW planning register
State significant development
- Application
- SSD-71368959
- Current stage
- Determination (register checked 2 Nov 2026)
- Decision
- Approved
- Determination date
- 22/12/2025
- Council
- Bayside
- Register page
- Project Duke Data Centre
402 days from exhibition to decision: longer than 11 of the 19 decided NSW data centre approvals.
Dated milestones
- 29 May 2024SEARs requested (first document uploaded)Dated by document upload time
- 31 May 2024SEARs issued (first document uploaded)Dated by document upload time
- 7 Nov 2024EIS lodged (first document uploaded)Dated by document upload time
- 15 Nov 2024EIS exhibition startsDated by assessment report
- 15 Nov 2024Notice of exhibition publishedDated by document upload time
- 12 Dec 2024EIS exhibition closesDated by assessment report
- 22 Dec 2025Determined: ApprovedDated by page field
- 23 Dec 2025Determination documents first publishedDated by document upload time
Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.
Stage changes we've recorded
No stage change since our captures began on 8 October 2026.
NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.