Project Atlas Data Centre
Campus in Eastern Creek, NSW · Goodman Group
The record
- Status
- Contested
a material public, planning or community dispute is documented (not a prediction) - Capacity as stated
- 500 MVA application figure
- Operator
- Goodman Group
- Record type
- Campus
several buildings on one site - Location
- Eastern Creek, New South Wales
Show on the map (approximate) - Evidence grade
- SOLID
a primary document or direct operator disclosure confirms it - Last checked
- 21 Oct 2026
- NSW application
- SSD-101067971
- Source
- NSW Planning Portal
On the NSW planning register
State significant development
- Application
- SSD-101067971
- Current stage
- More Information Required (register checked 2 Nov 2026)
- Decision
- Not yet decided
- Determination date
- —
- Council
- Blacktown
- Register page
- Project Atlas Data Centre Eastern Creek
- 49 daysRequest for SEARs to SEARs issued
- 118 days (3.9 months)SEARs issued to EIS lodged
- 338 days (11.1 months)Still open: SEARs requested to today
Dated milestones
- 28 Nov 2025SEARs requested (first document uploaded)Dated by document upload time
- 16 Jan 2026SEARs issued (first document uploaded)Dated by document upload time
- 14 May 2026EIS lodged (first document uploaded)Dated by document upload time
- 9 Jun 2026Notice of exhibition publishedDated by document upload time
- 21 Sep 2026Response to submissions lodged (first document uploaded)Dated by document upload time
- 27 Oct 2026Stage changed to More Information Required (was Assessment)Dated by our capture
Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.
Stage changes we've recorded
No stage change since our captures began on 8 October 2026.
NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.
More
Track the whole pipeline. The quarterly pipeline report covers every sourced project, the decisions to watch and a spreadsheet.
Spotted something wrong or out of date? Tell us, with a source if you can. Material changes are dated in the corrections log.