RegularsAIData centre tracker

Facility/NSW/Determination

Project Apollo Data Centre Macquarie Park

Facility in Macquarie Park, NSW · Goodman Group

The record

Status
Committed
approved or otherwise committed, but construction isn't confirmed
Capacity as stated
~90 MVA initial load capacity
Operator
Goodman Group
Record type
Facility
one building or site
Location
Macquarie Park, New South Wales
Show on the map (approximate)
Evidence grade
SOLID
a primary document or direct operator disclosure confirms it
Last checked
8 Oct 2026
NSW application
SSD-74069708

On the NSW planning register

State significant development

Application
SSD-74069708
Current stage
Determination (register checked 2 Nov 2026)
Decision
Approved
Determination date
02/09/2026
Council
City of Ryde
Register page
Project Apollo Data Centre Macquarie Park

530 days from exhibition to decision: longer than 16 of the 19 decided NSW data centre approvals.

decidedmedian 37801 yr2 yr3 yr
Each tick in the top row is one decided application; the line below is this one. Every approval, timed.

Dated milestones

  1. 26 Jul 2024SEARs requested (first document uploaded)Dated by document upload time
  2. 2 Aug 2024SEARs issued (first document uploaded)Dated by document upload time
  3. 10 Mar 2025EIS lodged (first document uploaded)Dated by document upload time
  4. 21 Mar 2025EIS exhibition startsDated by assessment report
  5. 21 Mar 2025Notice of exhibition publishedDated by document upload time
  6. 17 Apr 2025EIS exhibition closesDated by assessment report
  7. 14 Oct 2025Response to submissions lodged (first document uploaded)Dated by document upload time
  8. 15 Oct 2025Applicant's submissions report receivedDated by assessment report
  9. 2 Sep 2026Determined: ApprovedDated by page field
  10. 4 Sep 2026Determination documents first publishedDated by document upload time

Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.

Stage changes we've recorded

No stage change since our captures began on 8 October 2026.

NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.

More

Track the whole pipeline. The quarterly pipeline report covers every sourced project, the decisions to watch and a spreadsheet.

Spotted something wrong or out of date? Tell us, with a source if you can. Material changes are dated in the corrections log.