NEXTDC S5

Facility in Macquarie Park, NSW · NEXTDC

The record

Status
Proposed
announced or lodged for approval
Capacity as stated
80 MW80+ MW
Operator
NEXTDC
Record type
Facility
one building or site
Location
Macquarie Park, New South Wales
Show on the map (approximate)
Evidence grade
REPORTED
it rests on a credible secondary source or the applicant's own description
Last checked
21 Oct 2026
NSW application
SSD-63168959
Source
NEXTDC

On the NSW planning register

State significant development

Application
SSD-63168959
Current stage
More Information Required (register checked 2 Nov 2026)
Decision
Not yet decided
Determination date
—
Council
City of Ryde
Register page
NEXTDC S5 Data Centre and Innovation Hub
  • 34 daysRequest for SEARs to SEARs issued
  • 197 days (6.5 months)SEARs issued to EIS lodged
  • 1123 days (36.9 months)Still open: SEARs requested to today

Dated milestones

  1. 5 Oct 2023SEARs requested (first document uploaded)Dated by document upload time
  2. 8 Nov 2023SEARs issued (first document uploaded)Dated by document upload time
  3. 23 May 2024EIS lodged (first document uploaded)Dated by document upload time
  4. 1 Aug 2024Notice of exhibition publishedDated by document upload time
  5. 11 Feb 2026Response to submissions lodged (first document uploaded)Dated by document upload time

Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.

Stage changes we've recorded

No stage change since our captures began on 8 October 2026.

NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.

More

Track the whole pipeline. The quarterly pipeline report covers every sourced project, the decisions to watch and a spreadsheet.

Spotted something wrong or out of date? Tell us, with a source if you can. Material changes are dated in the corrections log.