NEXTDC S4
Campus in Horsley Park, NSW · NEXTDC
The record
- Status
- Under construction
construction has started - Capacity as stated
- 250 MW250 MW (Phase 1 approved); Phase 2 134.4 MW on exhibition
- Operator
- NEXTDC
- Record type
- Campus
several buildings on one site - Location
- Horsley Park, New South Wales
Show on the map (approximate) - Evidence grade
- SOLID
a primary document or direct operator disclosure confirms it - Last checked
- 21 Oct 2026
- NSW application
- SSD-108864209
- Source
- NSW Planning Portal
On the NSW planning register
State significant development
- Application
- SSD-108864209
- Current stage
- Exhibition (register checked 2 Nov 2026)
- Decision
- Not yet decided
- Determination date
- —
- Council
- Fairfield City
- Register page
- NEXTDC S4 Data Centre Phase 2, Horsley Park
19 days and counting: early days; the quickest decided NSW data centre approval took 158 days.
Dated milestones
- 12 Mar 2026SEARs requested (first document uploaded)Dated by document upload time
- 8 Apr 2026SEARs issued (first document uploaded)Dated by document upload time
- 24 Aug 2026EIS lodged (first document uploaded)Dated by document upload time
- 13 Oct 2026EIS exhibition startsDated by page field
- 13 Oct 2026Notice of exhibition publishedDated by document upload time
- 13 Oct 2026Stage changed to Exhibition (was Prepare EIS)Dated by our capture
- 10 Nov 2026 · aheadExhibition closesDated by page field
Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.
Stage changes we've recorded
- 13 Oct 2026first seenNEXTDC S4 Data Centre Phase 2, Horsley ParkFairfield City
Prepare EISto Exhibition
NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.