RegularsAIData centre tracker

Campus/NSW/Assessment

Mamre Road data centre campus

Campus in Kemps Creek, NSW · Project proponent

The record

Status
Contested
a material public, planning or community dispute is documented (not a prediction)
Capacity as stated
1,000 MW1 GW power capacity (applicant description)
Operator
Project proponent
Record type
Campus
several buildings on one site
Location
Kemps Creek, New South Wales
Show on the map (approximate)
Evidence grade
REPORTED
it rests on a credible secondary source or the applicant's own description
Last checked
8 Oct 2026
NSW application
SSD-92743706

On the NSW planning register

State significant development

Application
SSD-92743706
Current stage
Assessment (register checked 2 Nov 2026)
Decision
Not yet decided
Determination date
—
Council
Penrith
Register page
Mamre Road Data Centre Campus
  • 65 days (2.1 months)Request for SEARs to SEARs issued
  • 110 days (3.6 months)SEARs issued to EIS lodged
  • 461 days (15.1 months)Still open: SEARs requested to today

Dated milestones

  1. 28 Jul 2025SEARs requested (first document uploaded)Dated by document upload time
  2. 1 Oct 2025SEARs issued (first document uploaded)Dated by document upload time
  3. 19 Jan 2026EIS lodged (first document uploaded)Dated by document upload time
  4. 6 Mar 2026Notice of exhibition publishedDated by document upload time
  5. 5 May 2026Response to submissions lodged (first document uploaded)Dated by document upload time
  6. 21 Oct 2026Stage changed to Assessment (was Response to Submissions)Dated by our capture

Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.

Stage changes we've recorded

  1. 21 Oct 2026first seen

    Response to Submissions to Assessment

NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.

More

Track the whole pipeline. The quarterly pipeline report covers every sourced project, the decisions to watch and a spreadsheet.

Spotted something wrong or out of date? Tell us, with a source if you can. Material changes are dated in the corrections log.