Facility/NSW/Determination
IC3 Super West (Talavera Road expansion)
Facility in Macquarie Park, NSW · Macquarie Data Centres
The record
- Status
- Under construction
construction has started - Capacity as stated
- Expansion
- Operator
- Macquarie Data Centres
- Record type
- Facility
one building or site - Location
- Macquarie Park, New South Wales
Show on the map (approximate) - Evidence grade
- SOLID
a primary document or direct operator disclosure confirms it - Last checked
- 8 Oct 2026
- NSW application
- SSD-24299707
On the NSW planning register
State significant development
- Application
- SSD-24299707
- Current stage
- Determination (register checked 2 Nov 2026)
- Decision
- Approved
- Determination date
- 19/01/2024
- Council
- City of Ryde
- Register page
- Talavera Road Data Centre Campus Expansion
792 days from exhibition to decision: longer than 17 of the 19 decided NSW data centre approvals.
Dated milestones
- 15 Jul 2021SEARs requested (first document uploaded)Dated by document upload time
- 10 Aug 2021SEARs issued (first document uploaded)Dated by document upload time
- 8 Nov 2021EIS lodged (first document uploaded)Dated by document upload time
- 18 Nov 2021EIS exhibition startsDated by assessment report
- 18 Nov 2021Notice of exhibition publishedDated by document upload time
- 15 Dec 2021EIS exhibition closesDated by assessment report
- 27 Nov 2023Recommendation documents first publishedDated by document upload time
- 19 Jan 2024Determined: ApprovedDated by page field
- 19 Jan 2024Determination documents first publishedDated by document upload time
Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.
Stage changes we've recorded
No stage change since our captures began on 8 October 2026.
NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.
More
Track the whole pipeline. The quarterly pipeline report covers every sourced project, the decisions to watch and a spreadsheet.
Spotted something wrong or out of date? Tell us, with a source if you can. Material changes are dated in the corrections log.