Facility/NSW/Determination
Honeman Close Data Centre
Facility in Huntingwood, NSW · Microsoft
The record
- Status
- Committed
approved or otherwise committed, but construction isn't confirmed - Capacity as stated
- 96 MW96 MW (register description)
- Operator
- Microsoft
- Record type
- Facility
one building or site - Location
- Huntingwood, New South Wales
Show on the map (approximate) - Evidence grade
- SOLID
a primary document or direct operator disclosure confirms it - Last checked
- 8 Oct 2026
- NSW application
- SSD-58601963
- Source
- NSW Planning Portal
On the NSW planning register
State significant development
- Application
- SSD-58601963
- Current stage
- Determination (register checked 2 Nov 2026)
- Decision
- Approved
- Determination date
- 01/10/2026
- Council
- Blacktown
- Register page
- Honeman Close Data Centre
1022 days from exhibition to decision: longer than 18 of the 19 decided NSW data centre approvals.
Dated milestones
- 22 May 2023SEARs requested (first document uploaded)Dated by document upload time
- 2 Jun 2023SEARs issued (first document uploaded)Dated by document upload time
- 9 Nov 2023EIS lodged (first document uploaded)Dated by document upload time
- 14 Dec 2023EIS exhibition startsDated by assessment report
- 14 Dec 2023Notice of exhibition publishedDated by document upload time
- 1 Feb 2024EIS exhibition closesDated by assessment report
- 21 Feb 2024Response to submissions lodged (first document uploaded)Dated by document upload time
- 20 Aug 2024Applicant's submissions report receivedDated by assessment report
- 1 Oct 2026Determined: ApprovedDated by page field
- 2 Oct 2026Determination documents first publishedDated by document upload time
Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.
Stage changes we've recorded
No stage change since our captures began on 8 October 2026.
NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.
More