Facility/NSW/Assessment
GreenSquareDC SYD1 expansion (Brookhollow Avenue)
Facility in Norwest, NSW · GreenSquareDC
The record
- Status
- Proposed
announced or lodged for approval - Capacity as stated
- Capacity not stated on portal
- Operator
- GreenSquareDC
- Record type
- Facility
one building or site - Location
- Norwest, New South Wales
Show on the map (approximate) - Evidence grade
- REPORTED
it rests on a credible secondary source or the applicant's own description - Last checked
- 8 Oct 2026
- NSW application
- SSD-81928961
- Source
- NSW Planning Portal
On the NSW planning register
State significant development
- Application
- SSD-81928961
- Current stage
- Assessment (register checked 2 Nov 2026)
- Decision
- Not yet decided
- Determination date
- —
- Council
- The Hills Shire
- Register page
- Brookhollow Avenue Data Centre Expansion, Norwest
- 11 daysRequest for SEARs to SEARs issued
- 442 days (14.5 months)SEARs issued to EIS lodged
- 583 days (19.2 months)Still open: SEARs requested to today
Dated milestones
- 28 Mar 2025SEARs requested (first document uploaded)Dated by document upload time
- 8 Apr 2025SEARs issued (first document uploaded)Dated by document upload time
- 24 Jun 2026EIS lodged (first document uploaded)Dated by document upload time
- 24 Jul 2026Notice of exhibition publishedDated by document upload time
- 31 Oct 2026Stage changed to Assessment (was Response to Submissions)Dated by our capture
Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.
Stage changes we've recorded
- 31 Oct 2026first seenBrookhollow Avenue Data Centre Expansion, NorwestThe Hills Shire
Response to Submissionsto Assessment
NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.
More
Track the whole pipeline. The quarterly pipeline report covers every sourced project, the decisions to watch and a spreadsheet.
Spotted something wrong or out of date? Tell us, with a source if you can. Material changes are dated in the corrections log.