GreenSquareDC SYD1 expansion (Brookhollow Avenue)

Facility in Norwest, NSW · GreenSquareDC

The record

Status
Proposed
announced or lodged for approval
Capacity as stated
Capacity not stated on portal
Operator
GreenSquareDC
Record type
Facility
one building or site
Location
Norwest, New South Wales
Show on the map (approximate)
Evidence grade
REPORTED
it rests on a credible secondary source or the applicant's own description
Last checked
8 Oct 2026
NSW application
SSD-81928961

On the NSW planning register

State significant development

Application
SSD-81928961
Current stage
Assessment (register checked 2 Nov 2026)
Decision
Not yet decided
Determination date
—
Council
The Hills Shire
Register page
Brookhollow Avenue Data Centre Expansion, Norwest
  • 11 daysRequest for SEARs to SEARs issued
  • 442 days (14.5 months)SEARs issued to EIS lodged
  • 583 days (19.2 months)Still open: SEARs requested to today

Dated milestones

  1. 28 Mar 2025SEARs requested (first document uploaded)Dated by document upload time
  2. 8 Apr 2025SEARs issued (first document uploaded)Dated by document upload time
  3. 24 Jun 2026EIS lodged (first document uploaded)Dated by document upload time
  4. 24 Jul 2026Notice of exhibition publishedDated by document upload time
  5. 31 Oct 2026Stage changed to Assessment (was Response to Submissions)Dated by our capture

Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.

Stage changes we've recorded

  1. 31 Oct 2026first seen

    Response to Submissions to Assessment

NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.