Facility/NSW/Determination
Grand Avenue Data Centre Expansion, Rosehill
Facility in Rosehill, NSW · Equinix
The record
- Status
- Committed
approved or otherwise committed, but construction isn't confirmed - Capacity as stated
- Capacity not stated on portal
- Operator
- Equinix
- Record type
- Facility
one building or site - Location
- Rosehill, New South Wales
Show on the map (approximate) - Evidence grade
- SOLID
a primary document or direct operator disclosure confirms it - Last checked
- 8 Oct 2026
- NSW application
- SSD-53338465
- Source
- NSW Planning Portal
On the NSW planning register
State significant development
- Application
- SSD-53338465
- Current stage
- Determination (register checked 2 Nov 2026)
- Decision
- Approved
- Determination date
- 16/12/2024
- Council
- City of Parramatta
- Register page
- Grand Avenue Data Centre Expansion, Rosehill
416 days from exhibition to decision: longer than 12 of the 19 decided NSW data centre approvals.
Dated milestones
- 10 Jan 2023SEARs requested (first document uploaded)Dated by document upload time
- 12 Jan 2023SEARs issued (first document uploaded)Dated by document upload time
- 4 Aug 2023EIS lodged (first document uploaded)Dated by document upload time
- 27 Oct 2023EIS exhibition startsDated by assessment report
- 27 Oct 2023Notice of exhibition publishedDated by document upload time
- 23 Nov 2023EIS exhibition closesDated by assessment report
- 30 Jul 2024Response to submissions lodged (first document uploaded)Dated by document upload time
- 16 Dec 2024Determined: ApprovedDated by page field
- 16 Dec 2024Determination documents first publishedDated by document upload time
Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.
Stage changes we've recorded
No stage change since our captures began on 8 October 2026.
NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.
More
Track the whole pipeline. The quarterly pipeline report covers every sourced project, the decisions to watch and a spreadsheet.
Spotted something wrong or out of date? Tell us, with a source if you can. Material changes are dated in the corrections log.