Facility/NSW/Determination
Goodman SYD01 (Lanceley Place)
Facility in Artarmon, NSW · Goodman Group
The record
- Status
- Under construction
construction has started - Capacity as stated
- 90 MW~61 MW IT / 90 MW secured power / 90 MVA (consent after Mod 2)
- Operator
- Goodman Group
- Record type
- Facility
one building or site - Location
- Artarmon, New South Wales
Show on the map (approximate) - Evidence grade
- REPORTED
it rests on a credible secondary source or the applicant's own description - Last checked
- 21 Oct 2026
- NSW application
- SSD-66777221
On the NSW planning register
State significant development
- Application
- SSD-66777221
- Current stage
- Determination (register checked 2 Nov 2026)
- Decision
- Approved
- Determination date
- 11/04/2025
- Council
- Willoughby City
- Register page
- Lanceley Place Data Centre, Artarmon
282 days from exhibition to decision: quicker than 14 of the 19 decided NSW data centre approvals.
Dated milestones
- 20 Dec 2023SEARs requested (first document uploaded)Dated by document upload time
- 23 Jan 2024SEARs issued (first document uploaded)Dated by document upload time
- 6 Jun 2024EIS lodged (first document uploaded)Dated by document upload time
- 3 Jul 2024EIS exhibition startsDated by assessment report
- 3 Jul 2024Notice of exhibition publishedDated by document upload time
- 30 Jul 2024EIS exhibition closesDated by assessment report
- 23 Oct 2024Applicant's submissions report receivedDated by assessment report
- 23 Oct 2024Response to submissions lodged (first document uploaded)Dated by document upload time
- 11 Apr 2025Determined: ApprovedDated by page field
- 11 Apr 2025Determination documents first publishedDated by document upload time
Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.
Stage changes we've recorded
No stage change since our captures began on 8 October 2026.
NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.