DigiCo SYD1 expansion
Facility in Ultimo, NSW · DigiCo Infrastructure REIT
The record
- Status
- Committed
approved or otherwise committed, but construction isn't confirmed - Capacity as stated
- 47.5 MW47.5 MW increase in power consumption
- Operator
- DigiCo Infrastructure REIT
- Record type
- Facility
one building or site - Location
- Ultimo, New South Wales
Show on the map (approximate) - Evidence grade
- SOLID
a primary document or direct operator disclosure confirms it - Last checked
- 8 Oct 2026
- NSW application
- SSD-69637456
- Source
- NSW Planning Portal
On the NSW planning register
State significant development
- Application
- SSD-69637456
- Current stage
- Determination (register checked 2 Nov 2026)
- Decision
- Approved
- Determination date
- 23/12/2025
- Council
- City of Sydney
- Register page
- DigiCo SYD1 Data Centre Expansion
235 days from exhibition to decision: quicker than 18 of the 19 decided NSW data centre approvals.
Dated milestones
- 11 Apr 2024SEARs requested (first document uploaded)Dated by document upload time
- 8 May 2024SEARs issued (first document uploaded)Dated by document upload time
- 10 Apr 2025EIS lodged (first document uploaded)Dated by document upload time
- 2 May 2025EIS exhibition startsDated by assessment report
- 2 May 2025Notice of exhibition publishedDated by document upload time
- 29 May 2025EIS exhibition closesDated by assessment report
- 17 Jun 2025Response to submissions lodged (first document uploaded)Dated by document upload time
- 2 Sep 2025Applicant's submissions report receivedDated by assessment report
- 23 Dec 2025Determined: ApprovedDated by page field
- 24 Dec 2025Determination documents first publishedDated by document upload time
Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.
Stage changes we've recorded
No stage change since our captures began on 8 October 2026.
NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.