Davis Road data centre

Campus in Wetherill Park, NSW · Project proponent

The record

Status
Under construction
construction has started
Capacity as stated
180 MW180 MW (approved application)
Operator
Project proponent
Record type
Campus
several buildings on one site
Location
Wetherill Park, New South Wales
Show on the map (approximate)
Evidence grade
SOLID
a primary document or direct operator disclosure confirms it
Last checked
21 Oct 2026
NSW application
SSD-59416728

On the NSW planning register

State significant development

Application
SSD-59416728
Current stage
Determination (register checked 2 Nov 2026)
Decision
Approved
Determination date
20/12/2024
Council
Fairfield City
Register page
Davis Road Data Centre (Cundall)

276 days from exhibition to decision: quicker than 15 of the 19 decided NSW data centre approvals.

decidedmedian 37801 yr2 yr3 yr
Each tick in the top row is one decided application; the line below is this one. Every approval, timed.

Dated milestones

  1. 29 Jun 2023SEARs issued (first document uploaded)Dated by document upload time
  2. 8 Feb 2024EIS lodged (first document uploaded)Dated by document upload time
  3. 19 Mar 2024EIS exhibition startsDated by assessment report
  4. 19 Mar 2024Notice of exhibition publishedDated by document upload time
  5. 15 Apr 2024EIS exhibition closesDated by assessment report
  6. 2 Sep 2024Applicant's submissions report receivedDated by assessment report
  7. 2 Sep 2024Response to submissions lodged (first document uploaded)Dated by document upload time
  8. 20 Dec 2024Determined: ApprovedDated by page field
  9. 20 Dec 2024Determination documents first publishedDated by document upload time

Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.

Stage changes we've recorded

No stage change since our captures began on 8 October 2026.

NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.