Campus/NSW/Determination
CDC Marsden Park campus
Campus in Marsden Park, NSW · CDC Data Centres
The record
- Status
- Under construction
construction has started - Capacity as stated
- 504 MW504 MW (approved application)
- Operator
- CDC Data Centres
- Record type
- Campus
several buildings on one site - Location
- Marsden Park, New South Wales
Show on the map (approximate) - Evidence grade
- SOLID
a primary document or direct operator disclosure confirms it - Last checked
- 21 Oct 2026
- NSW application
- SSD-70889211
- Source
- NSW Planning Portal
On the NSW planning register
State significant development
- Application
- SSD-70889211
- Current stage
- Determination (register checked 2 Nov 2026)
- Decision
- Approved
- Determination date
- 27/11/2025
- Council
- Blacktown
- Register page
- Marsden Park Data Centre
378 days from exhibition to decision: quicker than 10 of the 19 decided NSW data centre approvals.
Dated milestones
- 16 May 2024SEARs requested (first document uploaded)Dated by document upload time
- 11 Jun 2024SEARs issued (first document uploaded)Dated by document upload time
- 4 Nov 2024EIS lodged (first document uploaded)Dated by document upload time
- 14 Nov 2024EIS exhibition startsDated by assessment report
- 14 Nov 2024Notice of exhibition publishedDated by document upload time
- 11 Dec 2024EIS exhibition closesDated by assessment report
- 28 Mar 2025Applicant's submissions report receivedDated by assessment report
- 28 Mar 2025Response to submissions lodged (first document uploaded)Dated by document upload time
- 27 Nov 2025Determined: ApprovedDated by page field
- 28 Nov 2025Determination documents first publishedDated by document upload time
Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.
Stage changes we've recorded
No stage change since our captures began on 8 October 2026.
NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.