Campus/NSW/Amend SEARs
CDC Data Centre Campus, Kemps Creek (KC1)
Campus in Kemps Creek, NSW · CDC Data Centres
The record
- Status
- Proposed
announced or lodged for approval - Capacity as stated
- 1,400 MWUp to 1.4 GW total power consumption (six buildings; application description)
- Operator
- CDC Data Centres
- Record type
- Campus
several buildings on one site - Location
- Kemps Creek, New South Wales
Show on the map (approximate) - Evidence grade
- SOLID
a primary document or direct operator disclosure confirms it - Last checked
- 27 Oct 2026
- NSW application
- SSD-133677993
- Source
- NSW Planning Portal
On the NSW planning register
State significant development
- Application
- SSD-133677993
- Current stage
- Amend SEARs (register checked 2 Nov 2026)
- Decision
- Not yet decided
- Determination date
- —
- Council
- Penrith
- Register page
- CDC Data Centre Campus, Kemps Creek
- 27 daysRequest for SEARs to SEARs issued
- 110 days (3.6 months)Still open: SEARs requested to today
Dated milestones
- 14 Jul 2026SEARs requested (first document uploaded)Dated by document upload time
- 10 Aug 2026SEARs issued (first document uploaded)Dated by document upload time
Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.
Stage changes we've recorded
No stage change since our captures began on 8 October 2026.
NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.
More
Track the whole pipeline. The quarterly pipeline report covers every sourced project, the decisions to watch and a spreadsheet.
Spotted something wrong or out of date? Tell us, with a source if you can. Material changes are dated in the corrections log.