Campus/NSW/Determination

AirTrunk SYD3 (51 Huntingwood Drive)

Campus in Huntingwood, Western Sydney, NSW · AirTrunk

The record

Status
Under construction
construction has started
Capacity as stated
400 MW400 MW total power consumption
Operator
AirTrunk
Record type
Campus
several buildings on one site
Location
Huntingwood, Western Sydney, New South Wales
Show on the map (approximate)
Evidence grade
REPORTED
it rests on a credible secondary source or the applicant's own description
Last checked
8 Oct 2026
NSW application
SSD-41589232

On the NSW planning register

State significant development

Application
SSD-41589232
Current stage
Determination (register checked 2 Nov 2026)
Decision
Approved
Determination date
15/09/2023
Council
Blacktown
Register page
51 Huntingwood Drive Data Centre

238 days from exhibition to decision: quicker than 17 of the 19 decided NSW data centre approvals.

decidedmedian 37801 yr2 yr3 yr
Each tick in the top row is one decided application; the line below is this one. Every approval, timed.

Dated milestones

  1. 21 Apr 2022SEARs requested (first document uploaded)Dated by document upload time
  2. 2 May 2022SEARs issued (first document uploaded)Dated by document upload time
  3. 16 Sep 2022EIS lodged (first document uploaded)Dated by document upload time
  4. 19 Jan 2023Notice of exhibition publishedDated by document upload time
  5. 20 Jan 2023EIS exhibition startsDated by assessment report
  6. 16 Feb 2023EIS exhibition closesDated by assessment report
  7. 28 Feb 2023Response to submissions lodged (first document uploaded)Dated by document upload time
  8. 12 May 2023Applicant's submissions report receivedDated by assessment report
  9. 15 Sep 2023Determined: ApprovedDated by page field
  10. 15 Sep 2023Determination documents first publishedDated by document upload time

Dated by the project page, the upload time the portal stamps on each document, the department's assessment report, or our own captures. How long approvals take.

Stage changes we've recorded

No stage change since our captures began on 8 October 2026.

NSW register data: NSW Major Projects register (State significant development, "Data Storage"), © State of New South Wales and Department of Planning, Housing and Infrastructure, CC BY 4.0; captured weekly, parsed and compared by RegularsAI. Licence: CC BY 4.0. The NSW Government does not endorse RegularsAI.

More

Track the whole pipeline. The quarterly pipeline report covers every sourced project, the decisions to watch and a spreadsheet.

Spotted something wrong or out of date? Tell us, with a source if you can. Material changes are dated in the corrections log.